Utility Shifting Along The Route Alignment of Dhaka Elevated Expressway Project.


01/Jun/2017


1. Total Length. 46.73km.

2. Location of the Project. DCC Area.

3. Objectives of the Project (Please specify). The main objectives of the project is to support implementation of Dhaka  Elevated Expressway  Projection the following components:

(a) Land acquisition and resettlement.

(b) Relocation of existing utilities (DWASA, DPDC, BTCL, Titas etc.) to construct the Dhaka Elevated Express way from Hazrat Shahjalal International Airport to Kutubkhali of Dhaka- Chittagong Highway.

(c) Consultancy for feasibility study, land acquisition, Environment & Social Assessment, Financial modeling, transaction & legal advisory functions.

(d) Supervision of Construction activities of PPP Project through Independent Engineer etc.