Mirpur Sher-E-Bangla National Cricket Stadium and Maj Rds of Dhaka City For Icc World Cup T-20 BD, 2014.
01/Jun/2017
1. Govt of the People’s Republic of BD, Ministry of LGRD and Cooperatives has entrusted the Corps of Engrs, BD Army to execute the task of "Impv of Rd Infrastructure and Beautification Wks Around Mirpur Sher-e-Bangla National Cricket Stadium and Maj Rds of Dhaka City for ICC World Cup T-20 BD, 2014’’proj financed by Govt of BD (GOB) and Dhaka North City Corporation (DNCC). This complete project involves land dev, constr of new flexible pavement, widening of rd, constr, dev and cleanliness of median and drainage sys, impv of footpath, impv of traffic sign, rd marking, rd lighting, divider and is land beautification wks etc. As per ‘Dev Proj Proposal’ (DPP) formulated by DNCC and approved in ECNEC, the estimated cost of this proj was Tk 11463.00 lacs and implementation pd is about 26 Jan 2014 to 30 Jun 2014 & RDPP is 12567.00lacs. Implementation pd was extended upto 31 Dec 2015. The proj is implemented as per Proj Implementation Policy (PIP) prepared by BD Army.
2. Prime Minister`s Office, AFD approved thedepl of BD Army for Impv of Rd Infrastructure and Beautification Wks aroundSher-e-Bangla National Cricket Stadium and maj Rds of Dhaka City for ICC WorldCup T-20 BD, 2014. This proj is implemented by 2 Engr Bn and 7 RE Bn under theoverall con of E in C through Engr Dteand under dir supervision of HQ 14 Indep Engr Bde.
a. |
Dt of Commencement |
: |
25 Jan 2014 |
b. |
Dt of Completion |
: |
31 Dec 2015 |
c. |
Proj Cost (RDPP) |
: |
12567.00 Lacs |
d. |
Fund Received (RDPP) |
: |
11683.40 Lacs |
e. |
Total Package |
: |
08 |
f. |
Physical Progress |
: |
99% |
g. |
Financial Progress |
: |
93% |